Pennsylvania Gov. Josh Shapiro signed an executive order imposing new requirements on large data centers.
Data centers will lose access to the state’s fast-track permitting program and face new transparency and local approval requirements.
The order calls for data centers to pay costs they impose on the electrical grid rather than passing them to other customers.
Pennsylvania Governor Josh Shapiro signed an executive order Tuesday imposing new restrictions on large AI data centers, including rules aimed at making developers pay for their impact on the state’s electrical grid.
Executive Order 2026-05 establishes new requirements for data centers with peak electricity demand above 25 megawatts. Developers seeking a streamlined state review must agree to Pennsylvania’s environmental, energy, workforce, and community requirements and obtain necessary local approvals.
Myriad: When will OpenAI release GPT-6? Click to make your prediction.
“I’m putting these developers on notice and letting them know that we will not let them bully Pennsylvanians, disregard our constitutional right to clean air and pure water, and drive up our utility bills,” Shapiro wrote on X. “I’m using the full weight of my executive authority to block the objectionable, unwarranted projects and put the nation’s strictest set of protections in place.”
The order also removes data centers from Pennsylvania’s Permit Fast Track Program and prohibits state agencies from signing non-disclosure agreements related to data center projects.
Pennsylvania will also create a public map of proposed facilities and require operating data centers to report their energy and water consumption annually beginning in July 2027.
The executive order also directs the state’s Special Counsel for Energy Affordability to seek utility rules making data centers cover certain grid costs and face curtailment first during some emergencies unless they secure enough power to meet their demand.
In the executive order, Shapiro noted that more than 100 data centers have reportedly been proposed in Pennsylvania, though only 20 have submitted permit applications to the state’s Department of Environmental Protection.
“From Archbald to Montgomery County to all across Pennsylvania, to your comments, texts, calls, and letters to my office, I’ve heard you loud and clear,” Shapiro wrote. “Pennsylvanians do not want AI data centers in their communities that would raise their utility costs and pollute their resources.”
Data center backlash
Opposition to AI data centers has spread across the U.S. as communities push back over electricity and the environmental impacts as more sites come online.
In January, a Brookings analysis warned that local resistance could slow or block AI infrastructure projects and called for binding community benefit agreements.
In March, Amazon, Google, Meta, Microsoft, OpenAI, Oracle, and xAI signed a White House pledge to pay for new electricity generation and infrastructure needed for their data centers as costs rose after the start of the U.S. led war with Iran.
The fight over data centers has increasingly moved to local governments. By August, at least 37 people had been arrested this year in protests tied to AI data centers across the U.S.
Daily Debrief Newsletter
Start every day with the top news stories right now, plus original features, a podcast, videos and more.
The FSNN News Room is the voice of our in-house journalists, editors, and researchers. We deliver timely, unbiased reporting at the crossroads of finance, cryptocurrency, and global politics, providing clear, fact-driven analysis free from agendas.
We and our selected partners wish to use cookies to collect information about you for functional purposes and statistical marketing. You may not give us your consent for certain purposes by selecting an option and you can withdraw your consent at any time via the cookie icon.
Cookies are small text that can be used by websites to make the user experience more efficient. The law states that we may store cookies on your device if they are strictly necessary for the operation of this site. For all other types of cookies, we need your permission. This site uses various types of cookies. Some cookies are placed by third party services that appear on our pages.
Your permission applies to the following domains:
https://fsnn.net
Necessary
Necessary cookies help make a website usable by enabling basic functions like page navigation and access to secure areas of the website. The website cannot function properly without these cookies.
Statistic
Statistic cookies help website owners to understand how visitors interact with websites by collecting and reporting information anonymously.
Preferences
Preference cookies enable a website to remember information that changes the way the website behaves or looks, like your preferred language or the region that you are in.
Marketing
Marketing cookies are used to track visitors across websites. The intention is to display ads that are relevant and engaging for the individual user and thereby more valuable for publishers and third party advertisers.